04Technical guide

Planning an AI/GPU-ready data hall

AI has broken the assumptions data halls were built on. A rack that used to draw 5 to 8 kW now draws 40, 80 or even 130 kW; air cooling runs out long before that; and the network between the GPUs matters more than the one to the outside world. This guide covers designing for it: power density, the cooling ladder, the 800GbE fabric and the physical design that holds it all up.

Vendor-neutral and educational. Figures are referenced from accelerator and system vendor specifications, ASHRAE, the Uptime Institute and IEEE 802.3; see the notes at the end.

Isometric drawing of three liquid-cooled GPU racks fed by a coolant distribution unit, with supply and return pipework overhead and an 800G fibre tray above. GPU rack ~132 kW CDU Coolant loop Supply Return 800G fabric
Fig. 04 / Liquid-cooled GPU row
Dwg
OX-RES-04
Rev
4.0
Scale
NTS
  • 16×A GB200-class rack (~132 kW) draws roughly 16 times a traditional enterprise rack
  • ~10kWA single 8-GPU AI server: a whole traditional rack of power in one box
  • 800GbEThe AI fabric: a non-blocking, ultra-low-loss leaf-spine carrying GPU east-west traffic
  • ~30kWThe practical ceiling for air cooling. Beyond it, liquid is not optional
  • ~1.1PUE reachable with liquid cooling, against ~1.5 for legacy air-cooled halls

01Why AI breaks the data hall

For twenty years, a data hall was a power and cooling problem solved at around 5 to 10 kW per rack. AI training rewrote that.

GPUs are power-dense by design: thousands of them, packed tight, running flat out for weeks, and they need to talk to each other at enormous bandwidth. The result is a facility where power density, liquid cooling and the internal network are the design, and everything else follows. A hall built for yesterday's densities cannot simply be upgraded for AI: the power, cooling and weight assumptions are different from the floor up.

Per-rack power by workloadIndicative
Air ceiling ~30 kW
~7 kW
~15 kW
~30 kW
~80 kW
~132 kW
Traditional enterpriseVirtualised / HCIAI inference / high densityAI training clusterGB200-class rack

The jump from virtualisation to AI training is not incremental. It is a step change of five to ten times that goes straight past what air can carry and into liquid cooling, reinforced floors and a different power and network design.

02The density problem, and what it demands

Everything starts with the power budget per rack, because it sets the cooling, the electrical distribution and even the structural design.

Drag the density below to see what a rack at that power needs: the cooling that can carry it, the heat it rejects and what it costs to run.

Interactive / Rack density and cooling calculator

Set the power per rack

Cooling methods light up where they can carry the load, and the readouts show the heat to reject and the annual energy.

30kW / rack

High density / AI inference

AI servers / rack~3 × 8-GPU
Heat to reject~30 kW
Energy / year~394 MWh

Cooling that can carry this density

At 30 kW, well-managed air can still cope.

03The cooling ladder: air to immersion

As density climbs, cooling moves from blowing cold air to bringing liquid ever closer to the silicon, because water carries roughly 3,500 times the heat of the same volume of air.

Each rung handles more heat, at more cost and complexity. Most AI halls today land on direct-to-chip liquid, often hybrid with air for the parts that do not need it.

MethodDensity ceilingHow it worksTrade-off
Air and containment~30 kWHot and cold-aisle containment with CRAC or CRAH unitsCheap and familiar, but runs out fast for AI
Rear-door heat exchanger~70 kWA water-cooled coil on the back of the rackA big step up that keeps the air model, but needs water to the rack
Direct-to-chip (DLC)~150 kWCold plates on the GPUs and CPUs, on a liquid loopThe AI workhorse: plumbing, CDUs and a leak-management regime
Immersion~200 kW+Servers submerged in dielectric fluidThe highest density and efficiency, and the biggest operational change
Density is not the only number

Ceilings are indicative and depend on coolant temperatures, rack layout and the specific equipment. Two numbers matter alongside density: PUE (liquid pushes it towards ~1.1, against ~1.5 for air) and water. Liquid cooling needs a facility water loop, coolant distribution units (CDUs) and a maintenance discipline that air never required. Designing the white space, the loop and the containment together is the difference between a hall that works and one that throttles. The liquid cooling guide covers the methods in depth.

04The 800G network that feeds the GPUs

In a traditional hall most traffic is north-south, in and out of the building. In an AI cluster it is overwhelmingly east-west: GPUs exchanging gradients with each other, constantly, at line rate.

A slow or congested fabric leaves very expensive GPUs sitting idle, so the network is built as a non-blocking, low-latency leaf-spine: today on 400/800GbE, heading to 1.6T.

800G leaf-spine fabric: two spine switches, each connected to all four leaf switches, each leaf feeding a GPU rack, with east-west traffic flowing between racks through the spine. Spine Leaf GPU Spine 1Spine 2 LeafLeafLeafLeaf

Every leaf reaches every spine, so any GPU can talk to any other at full bandwidth: non-blocking, east-west.

800G spine to leaf, ultra-low-loss fibreLeaf to GPU, in rackEast-west traffic

Traffic

East-west is the workload

GPU-to-GPU traffic dominates. The fabric has to be non-blocking, with full bandwidth between any two endpoints, or expensive accelerators stall waiting on the network.

Topology

Rail-optimised

AI fabrics are often wired so each GPU's NIC connects to its own “rail” of the network, spreading collective traffic evenly and keeping latency predictable across the cluster.

Loss budget

Low loss is non-negotiable

At 800G the optical loss budget is tiny. Ultra-low-loss connectors, clean MPO trunks and certified links are what let the fabric run at rate. The structured cabling guide explains why.

Density

Pre-terminated and dense

Base-8 and base-16 MPO trunks, pre-tested and ready to plug, handle the sheer fibre count of an AI fabric: faster to deploy and far cleaner to certify at scale.

05What holds it all up

Density does not just stress power and cooling. It changes the room.

A fully populated AI rack can weigh as much as a small car, draw three-phase power through busway, and demand containment and cable pathways planned around the liquid loop. The physical design is where an AI hall is won or lost.

Power

Power distribution

High-density rack PDUs fed from overhead busway, three-phase at the rack, and a power chain sized for sustained near-100% load: AI runs flat out, not in bursts.

Structure

Structure and weight

A loaded liquid-cooled rack can exceed 1,500 kg. Floor loading, plinth design and access routes have to be engineered for it; you cannot retrofit a slab.

Liquid

The liquid loop

CDUs, manifolds, leak detection and a facility water loop, designed alongside the white space rather than bolted on. Serviceability and redundancy of the loop become uptime-critical.

Air

Containment and airflow

Even liquid-cooled halls have an air component. Hot and cold-aisle containment, blanking and airflow management still matter for the heat that stays in air.

Cabling

Structured cabling at scale

Ultra-low-loss OM4 and OS2 and pre-terminated MPO trunks, designed for the 800G fabric and its breakouts, with the counts taken straight off the design model.

Layout

White-space planning

Rack layout, pathways, the loop and the fabric planned as one. Get the white-space design right and the hall scales; get it wrong and you strand power, cooling or ports.

Builds on the rest of the series

An AI hall is where the whole lifecycle converges. The 800G fabric rests on the fundamentals in the structured cabling guide, it has to be run to the disciplines in data centre operations, and the facility itself is chosen against the criteria in how to choose a data centre.

06How Optronix helps

AI and GPU halls are exactly the work we are built for: high-density, 800G, liquid-ready, designed and delivered end to end.

We design, supply, install, certify and migrate across the full data centre lifecycle, for hyperscale, colocation and enterprise clients across the UK, EMEA and worldwide. Power distribution, containment, the liquid loop and white-space fit-out are our everyday work.

Speed

Model-derived design, fast

We take a project from a single client drawing to a costed, model-derived design (densities, cooling, fabric and cabling counts) in under 48 hours. The counts come straight off the model, so the design you sign off is the one we build.

Assurance

Certified, warranty-backed cabling

The 800G fabric is installed as ultra-low-loss, pre-terminated, fully tested and certified plant, backed by a 25-year manufacturer system warranty through our accredited installer status with the major cabling manufacturers.

  1. 01

    Design and model

    Density, power, cooling strategy, fabric and cabling counts, modelled and costed from your drawing, fast, so decisions are made on real numbers.

  2. 02

    Supply and install

    Power distribution, containment, liquid-ready white space and the 800G cabling plant, supplied and installed by our own engineers, not subcontracted.

  3. 03

    Test and certify

    Every link tested and certified to standard, documented and warranty-backed, so the fabric runs at rate from day one.

  4. 04

    Migrate and operate

    Staged migration of live estates and ongoing operational support (smart hands, moves and changes) across the lifecycle.

AI and high-density builds

Send us the drawing and the target densities.

We will come back with a costed, model-derived design (power, cooling, 800G fabric and cabling) built to scale.

Share this guide with your team. Share on LinkedIn

Sources and notes

  • Rack densities and accelerator and system power from public GPU and AI-system vendor specifications (for example 8-GPU servers at ~10 kW; GB200 NVL72-class racks at ~120 to 132 kW).
  • ASHRAE TC 9.9 thermal guidelines and common industry practice for air, rear-door, direct-to-chip and immersion cooling density ceilings and PUE.
  • IEEE 802.3 (400/800GbE) and leaf-spine and rail-optimised fabric design as used in AI clusters; cabling per TIA-942 and ISO 11801 (see our structured cabling guide).
  • Uptime Institute on facility power, water and operations for high-density compute.